A Process Designed
For Quality

From site measure to installation, every stage is streamlined to ensure accuracy, speed and superior craftsmanship.

Our Process

From site measure to installation, our process is built for accuracy, efficiency and high-quality results every time.

01

Site Measure

Timeframe: 1 week

We schedule site measures approximately one week in advance.Our team can complete 2–3 measures per day, ensuring accurate dimensions and site conditions are captured for your project.
This foundation allows every stage that follows to run smoothly and without delay.

02

Shop Drawings

Timeframe: 1 week
  • 2–3 days for full CAD drafting
  • 1 day for site engineer review and approval
  • Check-measures arranged if required

We convert your site data into detailed technical drawings that guide fabrication and guarantee precision.

03

Materials Procurement

Timeframe: 1 week

After drawing approval, we compile material lists, generate component drawings, and place all required orders.
All materials are locally sourced within Australia, ensuring quality, consistency and fast turnaround.
Processing begins as soon as supplies arrive.

04

Fabrication

Timeframe: 1 week

With five dedicated fabrication stations, each project is assigned to the most suitable and experienced team.
This phase includes cutting, assembly, welding, polishing
and full QC checks against your approved drawings.
Once fabrication is complete, installation scheduling begins.

Additional Processing

Powder Coating

+1 week

Includes pick-up and drop-off, surface cleaning, powder application, oven curing and final quality inspection.

Curved Glass

+8 week

Requires template cutting and test-fitting before final curved glass is produced.

Laser-Cut Components

+1–2 weeks

Varies depending on material, thickness and design complexity (plate or tube laser cutting).

Laser-Cut Components

+1–2 weeks

Varies depending on material, thickness and design complexity (plate or tube laser cutting).

Glass Processing

+1–2 weeks

Based on shape, thickness, number of layers, laminate type and whether glass is straight or raking.

Hot Dip Galvanising

+3–4 weeks

Lead time depends on supplier capacity and backlog. Expedited options may be available.

Bending Components

+1–2 weeks

Dependent on material type, radius, quantity and template requirements.

Bending Components

+1–2 weeks

Dependent on material type, radius, quantity and template requirements.

Our Projects

Custom Metalwork & Balustrades,
Built for You

Get In Touch

For quotations, site visits, engineering queries or general project enquiries, complete the form below and our team will respond promptly.